Prepared for
Shark Bay Resources Pty Ltd
Useless Loop · Heirisson Prong · Shark Bay, Western Australia
Project
Bitterns Recycling — Field Piping Installation
SOW 7.1 & 7.7

Traffic Management
Plan

Document numberDTL-PRJ0072-TMP-001
RevisionA — Issued for Approval
Date16 July 2026
AttentionMr John Stephens — Principal Representative
Scope of work23092-SOW-024rD §7.1, 7.7
Submitted underSOW 7.1 — traffic management, barricading, signs & notices for the work areas
DTL (WA) Pty Ltd · 2/28 Horus Bend, Bibra Lake WA 6163 · ABN 45 677 646 454 · Commercial-in-Confidence
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 1 of 6
Traffic Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-TMP-001
Rev A

§Document control

RevDateDescriptionByChkApp
A16 Jul 2026Issued to SBR for review & approvalSHTK 
Confirm with SBR: site speed limits, designated haul roads, parking/laydown, and any SBR traffic controls or permits that apply to the pipeline corridor and the flume/pond access roads. This Plan is finalised on that confirmation.

Approval

PREPARED — DTL
Tyson Knight
Director · Date
APPROVED — SBR
Principal Representative · Date
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 2 of 6
Traffic Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-TMP-001
Rev A

1Purpose & scope

This Plan describes how DTL controls vehicle and plant movements for the Bitterns pipeline installation so that people and plant are kept apart, SBR’s operations continue safely alongside the works, and the sensitive pond areas are protected. Submitted under SOW 7.1 (traffic management, temporary barricading, safety signs and notices) and addressing the interfaces in SOW 7.7.

2Controls

DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 3 of 6
Traffic Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-TMP-001
Rev A

3Interface management (SOW 7.7)

Sections of the work interface with SBR and other contractors, with planned traffic movements past the pipeline installation area. DTL manages each interface as follows:

InterfaceControl
SBR electricians (isolation, instrumentation & control)Coordinate access windows; permits and isolations confirmed before adjacent work; comms on shared UHF.
Project civil construction worksSequence and separate work fronts; agree shared-access rules at the daily pre-start.
SBR & other contractors at the flume / pond areasShared access and haul roads kept clear; give way to SBR operations; spotters where the corridor crosses a haul road.
Interface arrangements are confirmed at the SBR kick-off meeting and reviewed at daily pre-starts and weekly progress meetings (SOW 7.9).
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 4 of 6
Traffic Management PlanBitterns Recycling Project — Field Piping Installation
DTL-PRJ0072-TMP-001
Rev A

4Roles & monitoring

Supported by DTL-HSE-PRO-0016 Traffic Management Plan (procedure) and the Journey Management Plan (DTL-HSE-MAP-0001) for travel to and from site.
DTL (WA) Pty Ltd · Commercial-in-ConfidenceContract SBS10627 · PO 182113Page 5 of 6